This is the log I kept up until the weight and balance was done. It was at this point I considered the building phase complete. All that was left was testing.
I tried to log the hours as realistically as possible, leaving out the time spent setting up and testing ideas as well as study time.
It turns out that it took a little under 600 hours to complete this project. This probably could have been done in fewer calendar days, but I have a life too. Besides most of it was the dead of winter, what else to do?
Also, I bet I could do another one in less time. My wife refuses to bet me.....
Actually, many thanks must go to her as she supported me the whole time and even helped when I needed more hands.
Firefly Builder's Log
Date |
Notes |
Hours |
12-18-2013 |
Kit delivered by Partain Transportation. Truck could not get down driveway due to ice, so we used tractor and big trailer to shuttle the parts to the shop. One fuselage, two wings, two ailerons and one box of parts. | 2.0 |
12-19-2013 |
Finished cleaning off the workbench. Made a table out of saw horses to hold the second wing. Unboxed parts. Discovered no main gear wheels. | 3.0 |
12-20-2013 |
Did inventory of parts, everything is here except wheels and brakes. Called factory and found out that the wheels and brakes are being direct shipped from that supplier, and should arrive next week. Also got some other questions answered about the parts. Spent most of afternoon moving snow in driveway and yard. Assembled the tail wheel and installed tail spring and wheel assembly on kit. | 6.0 |
12-23-2013 |
Installed main gear legs on fuselage. Drilled pilot holes in lower axle fittings. Installed aileron torque tube and flapperon brackets. Cleaned the lube holes in controls and lubed controls. Installed throttle and choke levers. Installed bolts in fuselage ring to tail boom tube. Cleaned toe brake tubes. | 9.0 |
12-24-2013 |
Unfolded tail feathers. Worked on cable pulleys and elevator control. |
3.0 |
12-25-2013 |
Figured out how to install forward pulleys. Made one cable for elevator. |
4.0 |
12-26-2013 |
Made and installed rest of tail feather cables. Installed rudder pedal springs. |
6.0 |
12-26-2013 |
Installed windshield anchor nuts. Installed gas tank tray. |
2.0 |
1-2-2014 |
Wheels and brakes showed up. Worked on installation. |
4.0 |
1-3-2014 |
Installed axles and managed to get a 2° toe in. Installed brake cylinders, toe brake brackets and master cylinders. Test fitted nose bowl. |
6.0 |
1-8-2014 |
Installed seat. Trimmed brake pedals to fit in cowling. Installed brake lines and bled brakes. |
6.0 |
1-9-2014 |
Worked on cowling mounting strips. Adjusted and final installed brake pedals and master cylinders. |
6.0 |
1-10-2014 |
Installed cowling mounting strips. Engine turned floor plate and trimmed to fit. Installed floor plate. |
4.0 |
1-15-2014 |
Worked on cowling fasteners. |
3.0 |
1-16-2014 |
Finished fitting cowling and drilled all mounting holes. Made floor/spacer plate for under heel area. |
3.0 |
1-22-2014 |
Re-arranged shop and mounted the wings. Temporarily installed ailerons. |
3.0 |
1-24-2014 |
Made final paint scheme and color decisions. Ordered covering materials. |
N/A |
1-30-2014 |
Drilled and temporarily fitted aileron control horns. Temporarily installed and tested aileron control tubes. |
3.0 |
1-31-2014 |
Worked on ailerons and flaperons. |
4.0 |
2-5-2014 |
Fitted flaperon controls. Marked hinges on wing and rudder. |
3.0 |
2-6-2014 |
Paint and fabric arrived. Loaded misc. un-installed parts in the seat and weighed the empty airframe. No covering, no engine, no instruments, no windshield. = 164 lbs. Sorted supplies, worked on iron, cleaned shop. |
4.0 |
2-7-2014 |
Made fabric test frames. Calibrated iron. Tested one frame with old fabric and glue. |
N/A |
2-12-2014 |
Removed ailerons, wings and nose cone for covering. Unhooked rudder cables. Removed struts from wings. Varnished plywood floor plate. | 3.0 |
2-12-2014 |
Worked on more fabric test covering. |
N/A |
2-13-2014 |
Calibrated a different iron and practiced on more fabric. Fixed up an old bathroom vent fan to exhaust fumes outside. 50 CFM is not adequate for the full shop. Worked on setting up the dust collector as an exhaust fan. That much air exchange will probably require a different or additional head source. |
N/A |
2-19-2014 |
Finished installing dust collector as a vent fan. It moves 420 CFM which means it will change the air in the shop in 15 minutes. Have to crack the door a few inches to keep the fan from back drafting the furnace. This will require significant heating capacity when the furnace is turned off. Also worked on ice in the driveway. |
N/A
|
2-20-2014 |
Pesticide renewal class, also worked on ice in driveway. |
N/A |
2-21-2014 |
Moved hay into barn. Removed all tail feathers and tail wheel from Firefly. Re-calibrated iron; now two different thermometers agree. Collected and bagged misc. parts. Labeled tail cables. Cleaned up iron and work tables. Need to make two more test panels, one for rib stitching practice and one to demonstrate the pulling power of raw and different temperatures of heat shrinking. Then ready to start prepping control surfaces for covering. |
N/A |
2-26-2014 |
Worked on some more test panels. Tested ventilation and respirator system. Tested UPS batteries and put VT tools away. |
N/A |
2-27-2014 |
Removed and marked hinges from tail feathers. Cleaned covering bench. Cleaned and prepped elevators for covering. Started covering left elevator. |
6.0 |
2-28-2014 |
Covered other elevator and tightened both to 325° F. |
6.0 |
3-6-2014 |
Cleaned shop and work table for covering. Reviewed covering instructions. Installed exhaust hose under tables. |
N/A |
3-7-2014 |
Cleaned and prepped right wing. Started installing bottom fabric |
6.0 |
3-8-2014 |
Got the bottom fabric on and smoothed the edges. Installed the top fabric and shaped the root rib and bow areas. Need to re-glue a section near the tip and trim off excess at trailing edge. |
7.0 |
3-12-2014 |
Finished installing fabric on right wing. Took fabric up to 300° F but center three ribs were starting to bow sideways so quit there. |
8.0 |
3-14-2014 |
Cleaned and prepped left wing. Got bottom fabric nearly installed |
6.0 |
3-19-2014 |
Finished up the bottom fabric and installed the top fabric. Did 225° F pass on bottom fabric. Tidied up the edges and ironed out all the wrinkles on the glued areas. |
7.0 |
3-20-2014 |
Heat shrunk everything to 225° F. Started experimenting with rib stitching. |
2.0 |
3-21-2014 |
Practiced rib stitching. Installed reinforcing tape and pre-punched needle holes (melted through fabric and tape). Left wing ready to rib stitch. |
2.0 |
3-26-2014 |
Started rib stitching left wing. |
7.0 |
3-27-2014 |
Finished rib stitching of left wing. Cleaned off excess wax and heat shrunk fabric. Pre-coated reinforcing tapes and other areas with Poly Brush. Installed inspection rings. |
7.0 |
3-28-2014 |
Installed tapes and patches on bottom of left wing. Made patches for the right wing. Pre-coated the ribs areas on the top of the wing. Made and installed all the top rib tapes on the left wing. |
7.0 |
3-31-2014 |
Ironed all the rib tapes down; came out smooth. Decided to install tapes on the root rib; made and installed the bottom tape. |
3.0 |
4-1-2014 |
Installed top root rib tape and root rib overlap seam tape. Laid out and marked placement of perimeter tape and pre-coated with Poly Brush. Finished installing all the tapes. |
7.0 |
4-2-2014 |
Brushed on the first coat of Poly Brush on left wing. Started installing re-enforcing tapes on right wing. Laid out and marked all stitch locations and pre-punched most of the holes. |
6.0 |
4-3-2014 |
Finished pre-punching holes. Started rib stitching. |
2.0 |
4-4-2014 |
Finished rib stitching and laid out locations for inspection rings. |
6.0 |
4-9-2014 |
Installed inspection rings and wing fold re-enforcement. Installed patches. Made and installed bottom tapes. Made and installed top tapes on top side. Let dry overnight. |
8.0 |
4-10-2014 |
Ironed out all wrinkles and re-glued loose tapes. Laid out locations for all perimeter tapes. Made tapes and installed. Ironed out all wrinkles and lumps. Wing ready for cleaning and first full coat of Poly Brush. |
7.0 |
4-11-2014 |
Cleaned right wing and applied brush coat of Poly Brush to both sides. |
2.0 |
4-16-2014 |
Cleaned up all drips and ironed out all lumps on right wing. |
3.0 |
4-17-2014 |
Cleaned and prepped rudder and vertical stabilizers. Brushed on base coat of Poly Tak |
3.0 |
4-18-2014 |
Covered and shrunk rudder fabric. Covered and shrunk lower vertical stabilizer. |
6.0 |
4-23-2014 |
Cleaned and prepped both horizontal stabilizers for covering. |
3.0 |
4-24-2014 |
Covered and shrunk one stabilizer. Measured remaining fabric and checked layout of remaining surfaces. Glued down first two edges on second stabilizer. |
6.0 |
4-25-2014 |
Finished second stabilizer. Started covering top vertical stabilizer. |
7.0 |
4-30-2014 |
Finished vertical stabilizer. Cleaned and prepped all tail feathers for applying finishing tapes. |
6.0 |
5-1-2014 |
Measured and cut tapes for tail feathers. Ran out of 3" tape, cut some from strips of fabric, |
4.0 |
5-2-2014 |
Installed most tapes on one side of tail feathers. |
3.0 |
5-7-2014 |
Worked on tail feather tapes. |
5.0 |
5-9-2014 |
Worked on tail feather tapes. |
2.0 |
5-14-2014 |
Worked on tail feather tapes. |
8.0 |
5-15-2014 |
Continued working on tail feather tapes. |
7.0 |
5-16-2014 |
Finished installing all tapes on tail feathers, ready to clean and Poly Brush. |
7.0 |
5-21-2014 |
Cleaned all tail feathers and put on brush coat of Poly Brush. Ironed out all bubbles and drips. |
7.0 |
5-22-2014 |
Cleaned and prepped both ailerons. Applied base coat of Poly Tak. |
5.0 |
5-23-2014 |
Cut fabric and started covering aileron. |
2.0 |
5-26-2014 |
Built spray booth. Practiced with sprayer. Got two coats of Poly Brush on one side of all tail feathers. |
6.0 |
5-27-2014 |
Finished last two coats of Poly Brush on the last side of all tail feathers. Glued fabric on one aileron and got it shrunk all the way to 350°. Got started with fabric on second aileron. |
8.0 |
5-28-2014 |
Put two coats of Poly Tone on all the tail feathers. Finished second aileron covering and shrinking. Yellow paint not covering very well. Cut tape strips for aileron ribs. |
10.0 |
5-29-2014 |
Put third coat of yellow on tail feathers. Cleaned and prepped ailerons for tapes. Figured out how to make stands for wings while painting. Ordered engine base plate and mounts from Kolb. |
5.0 |
5-30-2014 |
Finished ironing out lumps on left wing. Prepped both wings for spraying. Sprayed on first coat of Poly Brush on top of both wings. Ran out of material. Had major runs and sags on one wing, lighting not perfect. Will have to wait for it to completely dry, then remove with reducer and repair. AARRRGGGGG! | 3.0 |
6-1-2014 |
Brushed on a coat of Poly Brush on areas where it was all stripped off. |
0.5 |
6-3-2014 |
Sprayed second coat of Poly Brush on tops of both wings. |
1.5 |
6-4-2014 |
Sprayed two coats of Poly Brush on bottoms of wings. Made stands to hold wings for painting. Worked on Ailerons. Cleared off fuselage and secured cables and controls out of the way. Alodined flap control bracket. |
6.0 |
6-5-2014 |
Masked off both wings for painting yellow. Set up stands and put on first coat of yellow Poly Tone on both sides of both wings. |
4.0 |
6-6-2014 |
Put two coats of yellow Poly Tone on both wings. Put one coat of epoxy white primer on flap control bracket. |
4.0 |
6-9-2014 |
Masked off wings for red tip paint. Put on first coat of red. |
3.0 |
6-10-2014 |
Put on second coat of red. Had runs and sags. :( |
1.5 |
6-11-2014 |
Re-masked both wings for black stripe. Painted two full coats of black and unmasked. Worked on aileron finish tapes. |
7.0 |
6-12-2014 |
Worked on ailerons. |
2.0 |
6-13-2014 |
Worked on ailerons. |
4.0 |
6-18-2014 |
Finished putting tapes on ailerons. |
4.0 |
6-19-2014 |
Did finish ironing on ailerons. Sprayed on coat of Poly Brush. |
3.0 |
6-20-2014 |
Masked off the yellow and red sections of both ailerons. Primed metal torque tube and flap slider tube with epoxy primer. Put two coats of yellow Poly Tone on ailerons and torque tubes. |
6.0 |
6-21-2014 |
Masked off both ailerons for red and sprayed on first coat. |
2.0 |
6-22-2014 |
Sprayed on second coat of red. |
.5 |
6-23-2014 |
Re-masked both ailerons for black paint. Put on first coat of black. |
1.5 |
6-24-2014 |
Put second coat of black on the ailerons. |
.5 |
6-25-2014 |
Unmasked ailerons and put them away. Prepped and primed nose cone and struts. Painted two coats of red Poly Tone on nose cone. Many runs and sags, must be sanded and redone. Inverted fuselage and glued on bottom fabric. Tightened through 225° F. |
9.0 |
6-26-2014 |
Sanded out all runs and sags on nose cone. Lightly painted instrument panel face and spot painted sanded areas. More runs. Put fuselage upright and smoothed out all glue wrinkles on bottom tubes. Installed rear fabric panel on fuselage. Pre-coated all longerons with Poly Tak. |
5.0 |
6-27-2014 |
Sanded out minor runs from last night and re-spot painted nose cone. More runs! AARRGGGG!!!! Installed and heat shrunk the last of the fuselage fabric. Managed to get the nose cone painted to an acceptable level. Dismantled paint booth. |
8.0 |
7-2-2014 |
Finished cleaning up and ironing fuselage fabric. Started installing patches and tapes. |
7.0 |
7-3-2014 |
Worked on tapes and patches. Ron White and Brad Kramer came over for an inspection. Used some JB Weld on the loose main gear axle bolt. |
4.0 |
7-4-2014 |
Installed fuselage top perimeter tapes. Started ironing down the edges. |
3.0 |
7-6-2014 |
Ironed out all the top longeron tapes. Brushed on a coat of Poly Brush on the top tapes only. |
2.0 |
7-9-2014 |
Brushed on a coat of Poly Brush on the rest of the tapes. Ironed out the entire fuselage. Experimented with using a roller to put Poly Brush on the bottom of the fuselage. Lots of bubbles; will have to wait to see how it dries. |
3.0 |
7-10-2014 |
Ironing with parchment paper and rubbing with reducer could not make the rolled-on Poly Brush look acceptable. Wound up masking off the entire fuselage and spraying on two coats of Poly Brush. |
8.0 |
7-11-2014 |
Masked off the black area on the fuselage, then masked off the red area. Sprayed on first coat of yellow using blush retarder as it was over 80° F. Put on second and third coats of yellow. Cleaned and prepped hinges for painting. | 6.0 |
7-12-2014 |
Re-masked for red paint. Put first coat of red on fuselage. |
1.5 |
7-13-2014 |
Put on second coat of red paint. |
.5 |
7-14-2014 |
Re-masked fuselage for black paint. Put on two coats of black. |
1.0 |
7-18-2014 |
Painted yellow hinges on one side. Masked off and painted the yellow on the struts. |
1.0 |
7-19-2014 |
Painted the other side of the yellow hinges. Masked the struts and painted the red. Painted the red hinges on one side. |
1.0 |
7-20-2014 |
Masked off and painted the black on the struts and hinges. |
1.0 |
7-21 thru 31 |
Goldwing and camper repairs. OSHKOSH!!! |
N/A |
8-1-2014 |
Removed vertical stabilizer brackets from boom tube. Primed and painted yellow and white. |
1.0 |
8-2-2014 |
Permanently install vertical stabilizer brackets on boom tube. Installed vertical stabilizers and elevator horn. Need info on rivet size for vertical stabilizers. Also need 3/16" rivets for tail ring. Installed aileron torque tube and flaperon tube. Permanently installed left elevator to left horizontal stabilizers. Started on right side. |
8.0 |
8-4-2014 |
Finished installing all hinges on tail parts. Mounted tail wheel. Mounted rudder and tail wheel steering springs. Tensioned elevator cables and installed cotter pins. Installed rudder cables and springs. Installed cotter pins. Installed horizontal/elevator sections and flying wires. Torqued elastic lock nuts and installed cotter pins. |
9.0 |
8-7-2014 |
Made a tail group folding support bracket. Installed engine mounts. Cleaned and polished the engine mount plate. Alodined it, too. |
4.0 |
8-15-2014 |
Started assembly of motor mount plate to motor. |
2.0 |
8-16-2014 |
Installed motor and intake manifold adaptor. Inspected carb boot. Disassembled carb and cleaned. Installed new carb kit parts. Installed on engine. Both throttle and choke cables are too short. |
4.0 |
8-18-2004 |
Worked on choke cable. |
1.0 |
8-23-2014 |
Installed fuel tank, fuel pump, primer bulb and all fuel lines. Made and installed bracket for carb primer, installed primer and lines. Tie-wrapped brake lines in place. Tied seat back into place. Safety wired elevator turnbuckles. Installed seatbelt/harness. |
7.0 |
8-24-2014 |
Milled a fork for the choke cable from a piece of aluminum. |
4.0 |
8-27-2014 |
Put stop on choke end of cable. Installed and adjusted. |
1.0 |
8-28-2014 |
Assembled new Warp Drive prop and test fitted to engine. |
2.0 |
8-30-2014 |
Worked on throttle cable. |
2.0 |
8-31-2014 |
Worked on throttle cable and lever. |
6.0 |
9-1-2014 |
Finished throttle lever cable end. Installed cable and adjusted. Designed, built and installed a throttle stop. Installed air filter and safety wired. Did more research on props and MOI. |
7.0 |
9-9-2014 |
Permanently attached aileron and strut to right wing. |
3.0 |
9-10-2014 |
Permanently attached aileron and strut to left wing. |
3.0 |
9-11-2014 |
Removed exhaust manifold for re-painting; made and installed cover for exhaust ports. Made nut plates for nose cone. Practiced installing aileron gap tape. |
3.0 |
9-15-2014 |
Worked on instrument layout. Mounted nose cone to plane. Started making pitot tube bracket. Worked on name decal. |
5.0 |
9-16-2014 |
Made poster board template of windshield. Aligned and fit template to nose cone. Transferred hole marks to windshield and drilled holes. Finished making pitot tube bracket. Sandblasted and painted exhaust parts with hi-temp paint. Cured paint in grill. |
6.0
|
9-17-2014 |
Called factory about exhaust mounts. Travis said he was shipping stuff today. Shopped for misc. items in town. Ordered voltage regulator and wiring connectors from LEAF. |
4.0 |
9-18-2014 |
Mounted and torqued exhaust manifold. Removed nose cone and mounted pitot bracket. Marked cutouts for airspeed and compass, cut out airspeed hole and drilled screw holes. |
6.0 |
9-19-2014 |
Cut hole for compass, messed up one screw hole. Installed pitot hose. Cut and painted removable pitot tube. Polished and alodined prop faceplate. |
4.0 |
9-20-2014 |
Figured out how to make static ports with beveled washers and rivets. Installed one on each side of nose bowl. Muffler mount plate from Travis arrived today, but no aluminum angle or spacers, so had to make a run to town for parts. Started laying out and making pieces for muffler installation. |
8.0 |
9-21-2014 |
Fit up muffler mounting plate. Made spacers and bushings for plate. Designed and made angle bracket, rubber mounts and stand off spacers for muffler. Test fit everything. Cleaned up rough edges on plate and angle. Cleaned and alodined both aluminum parts. Took pictures and sent email to Kolb factory to see if my setup is acceptable for use. |
10.0 |
9-22-2014 |
IVO prop and spacer arrived from Internet contact. All is well; sent payment. I now have a 2 blade IVO, a 3 blade IVO and a 3 blade WARP to experiment with. |
N/A |
9-24-2014 |
Installed muffler mount and torqued everything down. Had to modify the top engine shroud to make it fit properly. Installed WARP drive prop with spacer and set initial pitch to 13.5°. Torqued all bolts to specs, installed lock nuts on prop bolts and torqued to specs. Made mount for voltage regulator and installed mount and regulator. Started wiring for the regulator. |
8.0 |
9-25-2014 |
Installed aileron gap seals. Installed tail ring bolts, made rub block for one of the rudder cables so it would clear the ring bolt. Finished wiring for regulator. Installed strobe light. Installed aileron push tubes. Finished painting pitot tube. |
7.0 |
9-26-2014 |
Installed safety wire and RTV on exhaust springs. |
1.0 |
9-29-2014 |
GRT instruments arrived. Installed temperature probes and started working on wiring harness. |
3.0 |
9-30-2014 |
Cut hole for EIS display. Drilled holes for power switch and circuit breaker. Sprayed touch up paint. Started wiring and static line installation. |
4.0 |
10-1-2014 |
Finished static tubing. Mounted compass and airspeed indicator. Worked on switch wiring for EIS unit. |
2.0 |
10-2-2014 |
Installed switch and circuit breaker. Installed EIS unit. Mounted nose cone on plane. Put wiring in wire loom. Wired in engine sensors. Wired in tachometer wire and strobe light. Ran wire for ignition switch. |
7.0 |
10-3-2014 |
Finished wiring. Programmed and tested EIS module. Finished installing nose cone. Installed windshield. Waxed the bottoms of the wings. |
5.0 |
10-4-2014 |
Rolled fuselage out into the driveway. Unfolded tail. Brad Kramer came over and helped carry and attach wings. Installed wing gap seal velcro and gap seal. Marked and drilled hole in tail boom for wing fold support bracket. |
6.0 |
10-5-2014 |
Re-mounted tail wheel; corrected lean problem. Set up blocks for level flight attitude. Installed skid ball. Ordered Firefly and Serenity stickers. |
2.0 |
10-6-2014 |
Used 3 scales to do weight and balance. Rotated scales 3 times and did averages to counter any errors. Did W&B calculations and the CG is inside the envelope listed in the construction manual. Filled gas tank 1 gallon at a time and marked fuel levels for both level flight and on the ground. |
6.0 |
10-8-2014 |
Made and installed wing fold bracket plates on trailing edges. Started engine on the first pull! Adjusted prop pitch to 7° to get static RPM above 6000. May have to add a little more pitch. Problems with engine running too lean on the bottom end of the throttle. Ran engine for about an hour. |
6.0 |
10-9-2014 |
Removed carb to look for idle problem. Moved O-ring on idle mixture screw; all passages clear. Remounted and tested engine. Could now get the idle mixture to adjust properly. Did full engine break-in procedure. There is a lean problem in the mid-range throttle area. Can be corrected by adding fuel with the enricher circuit. Will have to try adjusting the main needle up one notch to see if that fixes it. Also the bowl gasket leaks slightly. |
|